23Power to acquire land

(1)The authorised undertaker may acquire compulsorily—

(a)so much of the land shown on the Parliamentary plans within the limits of deviation for the authorised works shown on those plans and described in the book of reference as may be required for the purposes of the authorised works, and

(b)so much of the land specified in columns (1) and (2) of Parts 1 and 2 of schedule 6 (being land shown on the Parliamentary plans and described in the book of reference) as may be required for the purpose specified in relation to that land in column (3) of those Parts of that schedule;

and may use any land so acquired for those purposes or for any other purposes connected with or ancillary to its tramway undertaking.

(2)This section is subject to sections 40 (Time limit for exercise of powers of acquisition), 24 (Powers to acquire new rights) and 26 (Temporary use of land for construction of works).