Search Legislation

Historic Environment (Wales) Act 2016

Changes over time for: Section 29

 Help about opening options

Alternative versions:

Changes to legislation:

Historic Environment (Wales) Act 2016, Section 29 is up to date with all changes known to be in force on or before 14 April 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to the whole Act associated Parts and Chapters:

29Temporary stop noticesE+W

This section has no associated Explanatory Notes

(1)After section 44A of the Planning (Listed Buildings and Conservation Areas) Act 1990 (c.9) insert—

44BTemporary stop notices

(1)This section applies where it appears to a local planning authority in Wales that—

(a)works have been or are being executed to a listed building in their area; and

(b)the works are such as to involve a contravention of section 9(1) or (2).

(2)The authority may issue a temporary stop notice if, having regard to the effect of the works on the character of the building as one of special architectural or historic interest, they consider it is expedient that the works are stopped immediately (or that part of them is).

(3)A temporary stop notice must be in writing and must—

(a)specify the works in question;

(b)prohibit execution of the works (or so much of them as is specified in the notice);

(c)set out the authority's reasons for issuing the notice; and

(d)include a statement of the effect of section 44C.

(4)A temporary stop notice may be served on a person who appears to the authority—

(a)to be executing the works or causing them to be executed; or

(b)to have an interest in the building.

(5)The authority must display a copy of the notice on the building; and the copy must specify the date on which it is first displayed.

(6)A temporary stop notice takes effect when the copy of it is first displayed in accordance with subsection (5).

(7)A temporary notice ceases to have effect—

(a)at the end of the period of 28 days beginning with the day on which the copy of it is first displayed in accordance with subsection (5); or

(b)if the notice specifies a shorter period beginning with that day, at the end of that period.

(8)But if the authority withdraws the notice before the time when it would otherwise cease to have effect under subsection (7), the notice ceases to have effect on its withdrawal.

(9)A local planning authority may not issue a subsequent temporary stop notice in relation to the same works unless the authority have, since issuing the previous notice, taken other enforcement action in relation to the contravention referred to in subsection (1)(b).

(10)The reference in subsection (9) to taking other enforcement action includes a reference to obtaining an injunction under section 44A.

(11)A temporary stop notice does not prohibit the execution of works of such description, or the execution of works in such circumstances, as the Welsh Ministers may by regulations prescribe.

44CTemporary stop notices: offence

(1)A person is guilty of an offence if the person contravenes, or causes or permits a contravention of, a temporary stop notice—

(a)which has been served on the person; or

(b)a copy of which has been displayed in accordance with section 44B(5).

(2)An offence under this section may be charged by reference to a day or to some longer period; accordingly, a person may, in relation to the same temporary stop notice, be convicted of more than one offence under this section by reference to different periods.

(3)In proceedings against a person for an offence under this section, it is a defence for the person to show that the person did not know, and could not reasonably have been expected to know, of the existence of the temporary stop notice.

(4)In proceedings against a person for an offence under this section, it is also a defence for the person to show—

(a)that works to the building were urgently necessary in the interests of safety or health or for the preservation of the building;

(b)that it was not practicable to secure safety or health or, as the case may be, the preservation of the building by works of repair or works for affording temporary support or shelter;

(c)that the works carried out were limited to the minimum measures immediately necessary; and

(d)that notice in writing justifying in detail the carrying out of the works was given to the local planning authority as soon as reasonably practicable.

(5)A person guilty of an offence under this section is liable on summary conviction, or on conviction on indictment, to a fine.

(6)In determining the amount of a fine to be imposed on a person convicted under this section, the court must in particular have regard to any financial benefit which has accrued or appears likely to accrue to the person in consequence of the offence.

44DTemporary stop notices: compensation

(1)A person who, on the day when a temporary stop notice is first displayed in accordance with section 44B(5), has an interest in the building is, on making a claim to the local planning authority within the prescribed time and in the prescribed manner, entitled to be paid compensation by the authority in respect of any loss or damage directly attributable to the effect of the notice.

(2)But subsection (1) applies only if—

(a)the works specified in the notice are not such as to involve a contravention of section 9(1) or (2); or

(b)the authority withdraws the notice other than following the grant of listed building consent, after the day mentioned in subsection (1), which authorises the works.

(3)The loss or damage in respect of which compensation is payable under this section includes a sum payable in respect of a breach of contract caused by the taking of action necessary to comply with the notice.

(4)No compensation is payable under this section in the case of loss or damage suffered by a claimant if—

(a)the claimant was required to provide information under a relevant provision; and

(b)the loss or damage could have been avoided if the claimant had provided the information or had otherwise co-operated with the planning authority when responding to the notice.

(5)In subsection (4)(a), each of the following is a relevant provision—

(a)section 16 of the Local Government (Miscellaneous Provisions) Act 1976;

(b)section 330 of the principal Act.

(2)In section 31 of that Act (general provisions as to compensation for depreciation under Part 1 of the Act), in subsection (2), for “and 29” substitute “ , 29 and 44D ”.

(3)In section 82A(2) of that Act (Crown application: exceptions), after paragraph (f) insert—

(fa)section 44C;.

(4)In section 88 of that Act (rights of entry), after subsection (3) insert—

(3A)Any person duly authorised in writing by a local planning authority in Wales may at any reasonable time enter any land for any of the following purposes—

(a)securing the display of a temporary stop notice (see section 44B);

(b)ascertaining whether a temporary stop notice is being complied with;

(c)considering any claim for compensation under section 44D.

(5)In subsection (4) of that section (entry by Valuation Office etc in connection with compensation claims), for “or 29” substitute “ , 29 or 44D ”.

(6)In section 88B of that Act (rights of entry: supplementary provisions), after subsection (1) insert—

(1A)Subsection (1) does not apply to a person authorised under section 88(3A) who intends to enter the land for either of the purposes mentioned in paragraphs (a) and (b) of that subsection.

(7)In Schedule 2 to that Act (lapse of building preservation notices)—

(a)in paragraph 2, for “or 43” substitute “ , 43 or 44C ”, and

(b)after paragraph 4 insert—

Any temporary stop notice served by the local planning authority with respect to the building while the building preservation notice was in force ceases to have effect.

(8)In Schedule 4 to that Act (further provisions as to exercise of functions by different authorities), in paragraph 7, in sub-paragraph (1), after “42,” insert “ 44D, ”.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area. The revised version is currently only available in English.

Original (As Enacted or Made) - English: The original English language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Original (As Enacted or Made) - Welsh:The original Welsh language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Notes

Text created by the Welsh Government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes accompany all Acts of the Welsh Parliament.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources