Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
For amendments relating to regulations and orders made by the Welsh Ministers, see Schedule 7.
In this Act—
“PCPA 2004” means the Planning and Compulsory Purchase Act 2004 (c. 5);
“TCPA 1990” means the Town and Country Planning Act 1990 (c. 8).
(1)The Welsh Ministers T may by regulations make consequential, incidental, transitional or saving provision for the purpose of giving full effect to, or in consequence of, any provision of this Act.
(2)Regulations under this section may amend, revoke or repeal any enactment contained in, or made under, primary legislation.
(3)The power to make regulations under this section is exercisable by statutory instrument.
(4)A statutory instrument containing (whether alone or with other provision) regulations under this section which amend or repeal an enactment contained in primary legislation may not be made unless a draft of the instrument has been laid before and approved by resolution of the National Assembly for Wales.
(5)A statutory instrument containing regulations under this section to which subsection (4) does not apply is subject to annulment in pursuance of a resolution of the National Assembly for Wales.
(6)In this section, “primary legislation” means—
(a)an Act of Parliament;
(b)an Act or Measure of the National Assembly for Wales.
(1)The following provisions come into force on the day on which this Act receives Royal Assent—
(a)Part 1;
(b)sections 56 and 57;
(c)this section;
(d)section 59.
(2)The following provisions come into force at the end of the period of two months beginning with the day on which this Act receives Royal Assent—
(a)section 55;
(b)Parts 3 to 8, so far as is necessary for enabling the Welsh Ministers to exercise any function of making regulations or orders by statutory instrument under any enactment as amended by those Parts.
(3)Nothing in subsection (2)(b) affects the operation of section 13 of the Interpretation Act 1978 (c. 30) (anticipatory exercise of powers) in relation to this Act.
(4)The following provisions come into force on such day as the Welsh Ministers appoint by order—
(a)Part 2;
(b)Parts 3 to 8, so far as they are not brought into force by subsection (2)(b).
(5)The power to make an order under subsection (4)—
(a)is exercisable by statutory instrument;
(b)includes power—
(i)to appoint different days for different purposes, and
(ii)to make transitional, transitory or saving provision in connection with the coming into force of a provision of this Act.
The short title of this Act is the Planning (Wales) Act 2015.
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area. The revised version is currently only available in English.
Original (As Enacted or Made) - English: The original English language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Original (As Enacted or Made) - Welsh:The original Welsh language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: