In the Metropolitan Borough of Wolverhampton—
Work No. 1—railway (1,442 metres in length), forming a single line of tramway, commencing by a junction with the Work No. 1 authorised by the No. 1 Act of 1992 at a point in Victoria Square 15 metres east of the commencement of that work, passing westwards along Lichfield Street, Queen Square and Darlington Street, southwards along School Street, eastwards along Cleveland Street and northwards along Garrick Street and terminating in Bilston Street by a junction with the Work No. 1 authorised by the Act of 1989 at a point 40 metres east of the junction of that street with Market Street and Garrick Street;
Work No. 1A—A railway (51 metres in length), forming a single line of tramway, commencing by a junction with the Work No. 1A authorised by the No. 1 Act of 1992 at a point in Pipers Row 5 metres south of its junction with Victoria Square, passing north-westwards and terminating by a junction with Work No. 1 at a point in Lichfield Street 15 metres north-west of its junction with Victoria Square;
Work No. 1B—A railway (73 metres in length), forming a single line of tramway, commencing by a junction with the Work No. 1A authorised by the No. 1 Act of 1992 at a point in Pipers Row 20 metres from its junction with Bilston Street and terminating by a junction with the Work No. 1 authorised by the Act of 1989 at a point in Bilston Street 50 metres south-east of that road junction;
Work No. 1C—A widening of Darlington Street and School Street on the south-eastern side of the junction of those streets between a point in Darlington Street 22 metres east of that street junction and a point in School Street 12 metres south of that street junction.
In the Metropolitan Borough of Wolverhampton—
Set back the footway and kerbline on the southern side of Darlington Street and the eastern side of School Street at the junction of those streets, and raise the level of the surface of those streets at that junction, between the points marked A1 and A2 on the deposited plans;
Set back the kerbline on the western side of School Street between the points marked A3 and A4 on the deposited plans;
Set back the kerbline on the northern side of Darlington Street at its junctions with Red Lion Street and Waterloo Road between the points marked A5 and A6 on the deposited plans;
Set back the kerbline on the eastern side of School Street and the northern side of Cleveland Street at the junction of those streets between the points marked A7 and A8 on the deposited plans;
Stop up and discontinue the pedestrian subway under School Street at its junction with Cleveland Street and Salop Street between the points marked A9 and A10 on the deposited plans;
Set back the kerbline on the northern side of Cleveland Street between the points marked A11 and A12 on the deposited plans.
Note: In the following descriptions—
“the South Staffordshire Railway” means the South Staffordshire Junction Railway (Dudley and Stourbridge).
In the Metropolitan Borough of Dudley—
Work No. 2—railway (1,235 metres in length), commencing by a junction with the Work No. 17 authorised by the No. 1 Act of 1992 at a point 58 metres south of the junction of Bourne Street with Birmingham Street (North), passing southwards and south-westwards through the Dudley Bus Station and land adjoining the western side of Porter’s Field, then south-westwards in tunnel for a distance of 163 metres under the roundabout at the junction of Birmingham Street (South), Trindle Road, Hall Street and King Street, then passing southwards through the Flood Street Car Park and across Campbell Street and Constitution Hill at points respectively 17 metres and 23 metres east of the junctions of each of those roads with Flood Street, then passing south-westwards over Work No. 2A and across New Road, then passing on the north-western side of that railway to a point 215 metres south-west of the said bridge carrying New Road over that railway;
Work No. 2A—A tunnel (89 metres in length) formed over the existing South Staffordshire Railway in place of the bridge carrying New Road over that railway, commencing at a point 69 metres north-east of the north-eastern side of that bridge and terminating at a point 8 metres south-west of the south-western side of that bridge, including reinstatement of New Road over the tunnel;
Work No. 3—railway (2,539 metres in length), commencing by a junction with Work No. 2 at its termination, passing south-westwards along the north-western side of the existing South Staffordshire Railway, under Cinder Bank at the northern end of the bridge carrying that road over that railway, then as a single line over the existing Parkhead Viaduct, then continuing on the north-western side of that railway, passing under Pedmore Road at the northern end of the bridge carrying that road over that railway, then over the Pensnett Canal and Canal Street at points respectively 5 metres and 7 metres west of the western sides of each of the existing bridges carrying that railway over that canal and that street and terminating at a point on the northern side of that railway 155 metres east of the bridge carrying Dudley Road over that railway, including bridges under Cinder Bank and Pedmore Road and bridges over the Pensnett Canal and Canal Street;
Work No. 3A—A railway (363 metres in length) forming a deviation of the existing South Staffordshire Railway, commencing by a junction with that railway at a point 110 metres north-east of the north-eastern end of the Parkhead Viaduct, passing as a single line over that viaduct and terminating by a junction with that railway at a point 104 metres south-west of the south-western end of that viaduct;
Work No. 4—railway (1,110 metres in length), commencing by a junction with Work No. 3 at its termination, passing south-westwards on viaduct from a point on the northern side of the existing South Staffordshire Railway, then over that railway at a point 95 metres east of the said bridge carrying Dudley Road over that railway, then southwards and south-eastwards, over Level Street at a point 50 metres west of its junction with Old Bush Street, to a point 105 metres south of Level Street, then continuing southwards and south-eastwards across Cottage Street at a point 100 metres east of its junction with Little Cottage Street and terminating at a point 15 metres north-east of the junction of Little Cottage Street (North) with Little Cottage Street (South), including the said viaduct.
In the Metropolitan Borough of Dudley—
Repair and refurbishment of the existing Parkhead viaduct;
Stop up and discontinue the footpath between Pedmore Road and Cochrane Road between the points marked B1 and B2 on the deposited plans and remove the existing stairway between those points, substituting therefor a new footpath and stairway between the points so marked B2 and B3.